Solar Power Plant 22.32 MWp

Philippines

Duration

4 months

Project Description

Turnkey EPC

Key Highlights

Deployed a three-legged module, mounting the structure with a combination of concrete ballast and pilling foundations to make the project site flood resistant

Conducted a detailed flood analysis and installed outdoor inverter stations with RCC beams to tackle the soft, mushy soil

Business Vertical

Solar

Solar Power Plant

Abu Dhabi

Solar Power Plant
14MWp

Maharashtra India