Project Brief:

  • 36 MW under REC scheme
  • India’s largest solar PV power plant under REC scheme as of 15th April’13
  • Commissioned in the record time of 115 days on March 2013
  • 132 kV double circuits
  • Poly crystalline modules of 245W, 250W and 900kW inverter
  • Turnkey EPC

Project Name

Giriraj Enterprises BAAP, Rajasthan

Location

Baap, Jodhpur, Rajasthan

Duration

NA

PMC

NA

Consultants

NA

Technology

Polycristalline

Execution date

March 2013