Project Brief:
In the late 1980s and in the 1990s, Manipur state laid great emphasis on the construction of Transmission lines and Power Sub-Stations at various important load centers to cater to the need of the people of the state. As a result the state has 7 (seven) nos. of 132/33 KV Sub-stations at strategic load centers in operation.
Recently, the state announced expansion of of 132/33 kV bays at Churachandpur substation, Manipur. This is part of capacity augmentation of 132/33kV Churachandpur substation by adding one 20 MVA, 132/33 KV Power Transformer. With respect to the construction of 132/33 kV Substation at Jiribam, Manipur, Sterling and Wilson was entrusted with the responsibility of turnkey EPC solution for the substation package of one 132 kV Transformer Bay, two 132 kV Feeder bay, one 132 kV Bus Coupler Bay and seven 33 kV Bays .
Scope of work
Engineering, procurement, Erection, Testing and Commissioning of 132/33 kV substation at Jiribam, Manipur on turnkey basis. Scope includes supply of 132kV and 33 kV substation equipment including 20 MVA Transformer, complete civil work.
Project Name
Electricity Department, Govt. of Manipur
Location
Jiri bam, Manipur
Duration
20 Months
PMC
Electricity Department, Govt. of Manipur
Consultants
NA