Project Brief:

Power Grid Corporation of India Ltd. (POWERGRID), Govt. of India Enterprise is responsible for bulk power transmission and distribution of electrical energy from various central government power projects to various utilities/beneficiaries and interconnecting regional grids, operating and maintaining the national electrical grid of India. It is established with mandate of “Establishment and operation of regional and national power grids to facilitate transfer of power within and across the regions with reliability, security and economy on sound commercial principles”, as its mission. POWERGRID is carrying out extension of existing 400kV Kashipur (PTCUL) substation under NRSS-XXI for termination of 400kV Bareilly- Kashipur and 400kV Roorkee-Kashipur D/C lines associated with various transmission schemes.

Our Scope:

Supply, erection, testing and commissioning of 4 numbers line bays and associated tie bays for termination of 400KV Bareilly-Kashipur and 400KV Roorkee-Kashipur D/C lines with major electrical equipment e.g. 400kV CB, CT, CVT, isolator, LA, line traps, PLCC equipment, control and relay panels, tower and equipment structures and other hardware materials, ACDB, DCDB, augmentation of existing busbar protection scheme, sub-station earthing, illumination, lightning protection, cabling work including associated civil work for tower and equipment foundations, switchyard panel room, cable trench and others.

Project Name

Extn. of 400kV Kashipur (PTCUL) Substation

Location

Kashipur, Uttarakhand

Duration

16 months

Client

Power Grid Corporation of India Limited

Scope of Work

Extension of existing 400KV Kashipur (PTCUL) S/S with provision of 4nos. Line bays & associated tie bays for termination of 400KV Bareilly-Kashipur and 400KV Roorkee-Kashipur D/C line

Contractual Commissioning Date

17th November, 2015

Actual Commissioning Date

Bareilly-1 & 2 Line Bays on 20th April, 2015 Roorkee-1 & 2 Line Bays on 12th August, 2015